Road Resurfacing In Progress

Road resurfacing started this morning. The schedule is: 

July 31st - Green Briar Drive, Larchwood Drive and Sheffield Drive
August 1st - Huntsman Lane and Symphony Lane
August 2nd - Bluerock Lane, Midway Lane and Stonybrook Drive
August 6th - Sunset Drive and Valley Road
August 7th - Ivy Drive, Whitpain Drive and Meade Road
August 8th - Pinecroft Place, Collins Place, and Aldrin Drive
August 9th - Batleson Road
August 13th - Brochant Circle and Burgandy Circle
August 14th - Belle Circle and Hallman Drive

Resurfacing will take place between 7 a.m. and 5 p.m. Expect delays when using these roadways during resurfacing operations. Please use alternate routes if possible.  

Residents will have access to their properties at all times. 

This schedule is tentative and contingent on weather conditions. If there are any weather delays, please expect work to commence the next work day.